The transition to renewable energy is a priority for both global and national energy policies. In Turkey, solar energy projects have gained significant momentum, driven by incentives, feed-in tariffs, and the abundant availability of solar resources. However, any company or individual seeking to develop a solar energy power plant must first secure the necessary licenses and permits, particularly from the Energy Market Regulatory Authority (EPDK). One of the key steps in this process is compiling the documentation required for a solar energy generation license. This article explains the essential documents, application procedures, legal requirements, and practical tips for obtaining a solar energy license.
1. Legal Framework
The primary legislation regulating solar energy licensing includes:
- Electricity Market Law No. 6446 – Governs electricity generation, transmission, and distribution licensing.
- Renewable Energy Law No. 5346 (YEK Law) – Promotes renewable energy projects and provides support mechanisms.
- EPDK Licensing Regulations – Detailed guidelines for application, evaluation, and issuance of generation licenses.
- Environmental Law No. 2872 – Sets environmental obligations, including the Environmental Impact Assessment (EIA).
- Zoning Law No. 3194 – Governs land use and construction permits.
- Occupational Health and Safety Law No. 6331 – Ensures safety measures during construction and operation.
2. When Is a Solar Energy License Required?
A solar energy license is mandatory for projects with a capacity exceeding 1 MW (megawatt). For unlicensed generation (under 1 MW), a simplified process applies, involving only grid connection agreements with distribution companies.
For licensed projects:
- The investor must apply to EPDK for a generation license.
- The license allows the investor to construct, operate, and sell electricity produced from solar energy.
3. Application Process Overview
Before diving into the required documents, it is essential to understand the application process:
- Preliminary Feasibility and Site Selection: Ensuring the land is suitable for a solar plant and conducting technical studies.
- Grid Connection Approval: Obtaining a connection capacity approval from TEİAŞ (Turkish Electricity Transmission Corporation) or the local distribution company.
- Preparation of Documentation: Compiling corporate, financial, technical, and environmental documents.
- EPDK Submission: Filing the license application to EPDK with the required fees.
- Evaluation and Decision: EPDK reviews the application and issues the license if all requirements are met.
4. Key Documents Required for a Solar Energy License
4.1. Corporate Documents
- Articles of Association – The company’s main incorporation document, explicitly stating energy generation as an activity.
- Trade Registry Gazette – Evidence of the company’s registration.
- Tax Certificate – Proof of tax registration with relevant authorities.
- Signature Circular – Authorized signatories who will represent the company during the licensing process.
4.2. Financial Documents
- Balance Sheets and Income Statements – Demonstrating the company’s financial stability.
- Bank Guarantee Letters or Capital Proofs – Showing sufficient capital for project implementation.
- Shareholder Information – Ownership structure and shareholding percentages.
4.3. Technical Documents
- Project Description File (PDF): A detailed report covering:
- Installed capacity (MWp).
- Solar panel technology (e.g., monocrystalline, polycrystalline).
- Layout and design of the solar plant.
- Expected annual energy output.
- Connection Agreement Draft: Preliminary agreement with TEİAŞ or distribution company.
- Single-Line Diagrams: Electrical drawings of the system.
- Geographical Maps and Land Layout Plans: Site coordinates, access roads, and topography.
4.4. Land Ownership Documents
- Title Deed (Tapu) or Lease Agreement: Proving that the applicant has full rights to use the land for solar plant installation.
- Zoning Status Certificate: Confirming that the land is suitable for energy production according to zoning regulations.
4.5. Environmental Documents
- EIA Report (Environmental Impact Assessment): Required for larger projects or in environmentally sensitive areas.
- EIA Exemption Certificate: For smaller projects not requiring a full EIA.
- Environmental Compliance Reports: Waste management, water usage, and environmental protection measures.
4.6. Municipal and Construction Permits
- Pre-Construction Permit: Approved by the local municipality.
- Infrastructure Permits: Including road access and drainage systems.
- Fire Safety Approval: Ensuring compliance with fire regulations.
5. Additional Supporting Documents
- Company Activity Certificate: Obtained from the Chamber of Commerce.
- Renewable Energy Resource Confirmation: Document proving the use of solar energy as the main source.
- YEKDEM Application (Optional): For projects applying to the Renewable Energy Resources Support Mechanism.
- Insurance Certificates: Covering potential construction risks.
6. Evaluation by EPDK
After submission, EPDK evaluates:
- Technical adequacy: Whether the proposed design meets grid and safety standards.
- Financial capability: Whether the company can fund the project.
- Environmental compliance: Whether the project adheres to environmental laws.
The evaluation period is typically 3 to 6 months, depending on the complexity of the project and completeness of documentation.
7. Common Mistakes and Challenges
- Incomplete Documentation: Missing documents or signatures can delay the process.
- Land Disputes: Lack of clear title deed or zoning conflicts.
- Grid Connection Delays: TEİAŞ may reject grid connection requests due to capacity limitations.
- Environmental Challenges: Failure to secure EIA approval or local objections.
8. Legal Tips for a Smooth Licensing Process
- Hire an Energy Law Expert: An experienced lawyer can ensure full compliance with EPDK regulations.
- Perform Due Diligence on Land: Ensure no legal disputes or zoning issues exist.
- Early Communication with TEİAŞ: Avoid grid-related delays by securing early approvals.
- Prepare Detailed Technical Reports: Clear and professional documentation speeds up the EPDK review.
9. Timeline for Licensing
- Feasibility and land acquisition: 2–4 months.
- Grid connection approvals: 3–6 months.
- EPDK licensing: 4–6 months.
- Construction and commissioning: 12–18 months.
Overall, obtaining a solar energy license and completing the project can take 18–30 months.
10. Conclusion
Obtaining a solar energy license in Turkey requires careful preparation of a comprehensive set of corporate, financial, technical, environmental, and municipal documents.
- Corporate readiness, land rights, and grid connection approval are the backbone of the process.
- EPDK’s rigorous review ensures that only qualified and compliant projects are granted licenses.
Key Takeaways:
- Begin document preparation early to avoid delays.
- Work with professional legal and technical consultants.
- Ensure alignment with Renewable Energy Law and EPDK standards.