Hydroelectric power plants (HEPPs) are among the most common and reliable forms of renewable energy generation, using water flow to produce electricity. In Turkey, hydroelectric power projects are heavily regulated, requiring a comprehensive set of licenses, permits, and approvals before construction and operation can commence. These requirements are designed to ensure the sustainable use of water resources, environmental protection, and safe integration into the national electricity grid.
This article explores the licenses and approvals required to establish a hydroelectric power plant, along with the relevant legal framework, application process, and common challenges investors face.
1. Legal Framework for Hydroelectric Power Plant Licensing
The licensing process for HEPPs is governed by several key laws and regulations:
- Electricity Market Law No. 6446: Defines the need for a generation license from the Energy Market Regulatory Authority (EPDK).
- Law No. 5346 on Renewable Energy (YEK Law): Provides incentives and regulatory support for renewable energy projects.
- Environmental Law No. 2872: Requires Environmental Impact Assessment (EIA) for projects above certain capacity thresholds.
- Water Law and DSİ (State Hydraulic Works) Regulations: Govern water usage rights and river basin management.
- Zoning Law No. 3194: Covers land-use planning, building permits, and construction licenses.
- Occupational Health and Safety Law No. 6331: Imposes workplace safety measures during construction and operation.
2. Main Licenses and Permits Required
Establishing a hydroelectric power plant involves multiple permits from national, regional, and local authorities. These include:
2.1. Generation License (EPDK)
- The primary license required for any energy generation facility over 1 MW capacity.
- Grants the right to generate and sell electricity for a specified term (usually 10–49 years).
- Issued by the Energy Market Regulatory Authority (EPDK) after a detailed review of technical, financial, and legal documents.
2.2. Water Usage Right Agreement (DSİ)
- DSİ (State Hydraulic Works) controls water resources in Turkey.
- Investors must obtain a water usage right agreement for the river or stream where the HEPP will be located.
- This agreement specifies:
- The amount of water that can be used.
- The environmental flow that must be maintained.
- Obligations for riverbed maintenance.
2.3. Environmental Impact Assessment (EIA)
- Mandatory for all hydroelectric plants with an installed capacity of 10 MW or more.
- Involves a detailed assessment of:
- Biodiversity and ecosystem impacts.
- Fish migration and aquatic life.
- Local communities and water quality.
- Results in either an “EIA Positive” decision or an “EIA Not Required” certificate for smaller projects.
2.4. Construction and Zoning Permits
- Zoning Plan Approval: Land must be designated for energy production.
- Construction Permit (İnşaat Ruhsatı): Issued by the municipality or provincial directorate.
- Occupancy Permit (Yapı Kullanma İzni): Granted upon successful completion of construction.
2.5. Connection and System Usage Agreements (TEİAŞ)
- To connect the plant to the national grid, the investor must:
- Obtain a connection agreement from TEİAŞ or the local distribution company.
- Sign a system usage agreement to ensure proper integration into the electricity network.
2.6. Water and Environmental Permits
- Riverbed Excavation and Construction Permit: DSİ approval for civil works.
- Fish Ladder or Aquatic Life Protection Permits: If the project impacts fish migration.
- Wastewater and Discharge Permits: Issued by the Ministry of Environment.
2.7. Additional Permits
- Forest Usage Permit: Required if the project area is within a forest zone.
- Expropriation Permits: If private lands must be acquired for construction.
- Mining or Excavation Permits: If materials are sourced from local quarries.
3. EPDK Generation License Application Process
The EPDK license application involves several steps:
- Preliminary Application: Submission of feasibility reports, financial statements, and project documents.
- Technical Evaluation: EPDK reviews the project’s design, capacity, and connection to the grid.
- Public Consultation: Local stakeholders may be consulted during the process.
- Final Approval and License Issuance: A generation license is issued, allowing the construction and operation of the HEPP.
4. Key Documents Required for Licensing
4.1. Corporate and Financial Documents
- Articles of association of the company.
- Trade registry records and tax certificates.
- Balance sheets, income statements, and proof of financial capability.
4.2. Technical Reports
- Feasibility study (hydrology, energy production forecasts).
- Engineering design documents.
- Grid connection feasibility report.
4.3. Environmental Documents
- EIA report or exemption certificate.
- Biodiversity and water quality assessments.
4.4. Land Ownership and Zoning Documents
- Title deeds or long-term lease agreements.
- Approved zoning plans for the construction site.
5. Timeline for Licensing and Permits
The entire licensing and permitting process typically spans:
- Feasibility and water rights agreement: 3–6 months.
- EIA preparation and approval: 6–12 months.
- EPDK license issuance: 6–9 months.
- Construction permits and TEİAŞ approvals: 3–6 months.
- Total timeframe: Approximately 18–30 months before construction can begin.
6. Challenges in Licensing Hydroelectric Projects
6.1. Environmental Concerns
- HEPPs can face strong opposition due to impacts on river ecosystems and local habitats.
- Failure to conduct proper environmental studies can lead to project delays or cancellations.
6.2. Land and Water Rights Disputes
- Overlapping claims on water usage rights can create legal challenges.
- Expropriation of private land can lead to litigation.
6.3. Technical and Grid Capacity Limitations
- TEİAŞ may limit connection capacity, requiring additional investment in infrastructure.
7. Legal and Strategic Advice for Investors
- Hire Energy Law Experts: Legal professionals can navigate the complex regulatory landscape.
- Conduct Early Feasibility Studies: Ensure that the selected river or site is technically and legally viable.
- Engage with Local Communities: Early engagement reduces opposition and smoothens the permitting process.
- Monitor Incentives: HEPPs may benefit from YEKDEM feed-in tariffs and other renewable energy incentives.
8. Conclusion
Establishing a hydroelectric power plant in Turkey requires multiple licenses and permits, primarily from EPDK, DSİ, and the Ministry of Environment.
- Generation licenses, water usage rights, EIA approvals, and zoning permits form the backbone of the regulatory process.
- Investors who plan and prepare their applications thoroughly can minimize delays and ensure legal compliance.
Key Takeaways:
- Start with DSİ water rights and EPDK licensing early in the process.
- Environmental and zoning compliance are critical to avoid disputes.
- Professional legal and technical support can significantly streamline the project timeline.