Buying a Wind Power Project in Türkiye: What to Check Before Signing a Share Purchase Agreement

Onshore wind turbines on rolling hills in western Türkiye

An investor acquiring a Turkish wind farm should confirm three things before signing a share purchase agreement: whether the transaction is permitted at the project’s current licensing stage, whether the company controls all rights needed to operate the facility, and whether the cash flows in the valuation can continue after closing. A share purchase may leave the same Turkish company holding the project, but it does not automatically preserve lender consents, contract terms, permitted capacity or access rights. A project that looks attractive on a generation chart can be a poor acquisition if one of those rights expires before the end of the forecast.

This guide addresses a foreign investor buying control of a privately held Turkish company with an onshore wind project. It distinguishes an operating farm from a development project where the investor is taking construction and permitting risk. It does not assume that unlicensed generation, offshore projects, public companies or tender-based projects follow the same rules. Where the target combines assets or several facilities in one company, carry out the analysis for each asset and contract rather than treating the company as a single project.

1. Before the offer: establish what the seller actually owns

Ask for a one-page map of the transaction perimeter: the seller, each intermediate holding company, the Turkish project company, its affiliates, the facility, the grid connection and each material contractual counterparty. Ask the seller to mark which items are owned by the target, leased to it, held by another group company or shared with a neighbouring project. A purchase of shares only transfers the ownership interests covered by the agreement; a right held elsewhere in the seller group must be dealt with separately.

Request the current production licence or preliminary licence, all amendments, the corporate register extracts and a direct and indirect ownership chart. Match the legal entity and facility identifiers against the grid agreement, the environmental file and the commissioning records. Compare permitted capacity, installed capacity and the capacity actually connected and earning revenue. Treat additions, repowering and capacity increases as separate items unless the data room shows the approvals, agreements and acceptance records on which the expansion relies. Consider valuing an expansion separately rather than paying for it as operating capacity.

The indicative offer should identify the assumptions that drive price: what capacity is operational, what revenue arrangements are in force, the remaining useful life and contracted availability of the turbines, and which land and evacuation rights continue for the forecast period. Separate business assumptions from facts that will be verified. A seller price built on uninterrupted operations, for example, should not be accepted before the buyer sees the connection documents, invoices and material claims history.

2. Map the licensing and ownership route before setting a timetable

The Turkish Energy Market Regulatory Authority (EPDK, also known as EMRA) distinguishes the preliminary licence from the production licence. The former is part of preparing a generation facility for licensing; the latter is the authority under the electricity-market framework to perform the licensed generation activity. Do not rely on marketing terms such as “ready to build,” “fully permitted” or “licence secured.” Ask to see the actual instrument and its conditions, including pending amendments, expiry dates, milestones and correspondence about compliance.

A preliminary licence is a particular warning sign for an acquisition. The Electricity Market Licensing Regulation restricts direct and indirect changes in a preliminary licence holder’s ownership before the production licence is obtained, subject to specific exceptions. Do not assume that an offshore holding-company transfer, staged purchase, option or minority investment avoids review. Map the ownership and control effects of each step and test them against the current consolidated rules before granting the buyer contractual rights. If there is no support for a permitted route, do not use a generic consent clause as a substitute for resolving the issue.

For an operating licensed project, determine which EPDK approval, notification or licence amendment, if any, is triggered by the proposed structure and the target’s activities. An approval rule for an entity whose tariff is regulated should not simply be carried across to every generator. Review the legal position for the actual licence holder and transaction, including any upstream change of control, pre-closing restructuring and arrangements for security over shares. An asset purchase or merger should be evaluated independently; it is not safe to assume the operating company’s licence follows equipment or land.

Create a short approvals register. For each requirement record the trigger, who applies, documents needed, whether it must be satisfied before completion, and what evidence will prove compliance. Distinguish a binding approval from a filing acknowledgement or a seller assurance. Agree who bears the cost of responding to a regulator and what happens if approval is granted subject to conditions that materially reduce the benefits the parties expected.

3. Check that the asset can keep operating and earning

Grid connection, system use and commissioning

Obtain the executed connection and system-use documentation and every relevant amendment from the transmission or distribution route applicable to the facility. Reconcile the connection point, permitted export capacity, metering arrangements, technical conditions and the allocation of responsibility for network works. Ask whether the evacuation line and substation are owned, shared or subject to access arrangements and whether any counterparty consent is required for the deal. Identify who pays for repairs, reinforcement or shared equipment and how disputes about availability are handled.

An operating licence is not a substitute for project-specific commissioning evidence. Obtain records showing which units and capacity have been accepted and when. Compare them with the facility plan, metering data and seller production model. Request correspondence on interruptions, network restrictions or capacity changes for a representative operating period. Distinguish a network constraint from a turbine fault: the two can call for different technical solutions, different contract claims and a different reduction in the buyer’s valuation.

Land, access and environmental compliance

Build a parcel-by-parcel schedule covering turbine foundations, crane pads, internal roads, cable corridors, substations, the evacuation route and access needed for maintenance and heavy component replacement. Obtain the underlying deeds, leases, easements or public-land instruments as applicable. Match their parties, scope, term and termination clauses to the site map. Record renewal dates, title restrictions, rent escalation, compensation and consent requirements. A right to place a turbine on one parcel does not establish a right to cross another parcel with a replacement blade.

Review the environmental impact assessment (ÇED) file, the applicable decision and project commitments, rather than relying on a cover page stating that the project is compliant. Check whether the approved project configuration matches the facility now operating and whether layout changes, extra turbines, infrastructure relocation or capacity increases have been assessed. Obtain environmental monitoring records and look for administrative challenges, fines, community complaints and unfulfilled commitments. The ministry updated its implementation guidance in March 2026; confirm the rules that apply to the target and any proposed changes.

Revenue support, offtake and operating costs

Identify the actual source of revenue. It may come from market sales, a bilateral power purchase agreement, renewable support under YEKDEM, or another arrangement applicable to the project. The existence of a national support programme does not prove the target participates or that the same economics will continue for the life of the buyer’s model. Where the price depends on YEKDEM, check the facility and licence details against the applicable list, then reconcile eligibility and term against the project records and actual settlement statements. Test the financial model without unverified support or with a conservative assumption after the supported period.

For contracted sales, read the agreement and amendments for pricing, currency, volume commitments, imbalance allocation, termination, default, security, expiry and change of control. Obtain a sample month of meter readings, invoices and cash receipts, then check whether they reconcile. Do not overlook related-party fees that disappear after closing or services that the buyer must replace. Where the transaction is financed, stress-test the model against curtailed generation, delayed collections, changes in exchange rates and major maintenance rather than relying on a single base case.

Review the turbine supply and operations and maintenance agreements together. Ask what equipment is still under warranty, who can assert claims, which maintenance obligations protect warranty coverage, and what remedy is available if a turbine is unavailable. Include historic major component replacements, unresolved serial-defect claims and upcoming service renewals in the capital expenditure assessment. Check whether insurance limits, deductibles and exclusions match lender requirements and the operating risks that the project actually faces.

4. Decide which findings change price, conditions or deal structure

Convert due diligence into a decision record. A quantifiable shortfall, such as a near-term service renewal at a higher known cost, can be reflected in the price or model. A missing right that prevents continued operation normally needs stronger protection, such as a documented cure before closing. A historic issue with a definable exposure may be addressed by a specific indemnity and security if the seller can support it. Where a material risk cannot be measured, cured or allocated on acceptable terms, a buyer should be prepared to defer the investment decision.

RiskEvidence to requestPossible transaction effect
Project is held at preliminary-licence stageCurrent licence instrument, ownership chart and applicable EPDK rulesDefer signing or revise the structure only if a permitted route is established.
Claimed output exceeds accepted capacityLicence amendments, grid agreement, acceptance records and meter dataExclude unaccepted capacity from the base price or separate contingent value.
Maintenance access expires earlyRegistered easement, lease or signed extension mapped to the access routeRequire a durable extension before closing or reassess operating value.
Debt or offtake may terminate on change of controlFinance and power sale contracts, amendments and written consentsMake closing conditional on consents, repayment or replacement arrangements.
Revenue depends on unverified supportApplicable YEK list, project eligibility basis and settlement recordsReprice or model a downside until the revenue basis is evidenced.

Competition clearance is a separate analysis from EPDK licensing and commercial consents. Türkiye’s Competition Authority amended the general merger thresholds in February 2026. Under the amended Article 7, the general routes include combined Türkiye turnover exceeding TRY 3 billion with at least two parties each exceeding TRY 1 billion in Türkiye, or, for an acquisition, turnover of the acquired asset or activity in Türkiye exceeding TRY 1 billion and another party’s global turnover exceeding TRY 9 billion. These are turnover tests, not deal-value tests. Determine whether the transaction falls within the control rules, which economic units count and how turnover is calculated. Check any special treatment and updated guidance rather than applying figures to a term sheet in isolation.

Check lender requirements in parallel. Ascertain whether the buyer is assuming the project’s debt, refinancing it or paying it off. Request the facility agreement, direct agreements, hedging documents, guarantees and security schedules. Agree the sequence for pay-off, release and any new security, including control of accounts and replacements for seller-group support. A lender’s informal indication is not equivalent to a signed consent or binding pay-off letter with a usable release mechanism.

5. Draft an SPA that reflects the real closing path

State the transaction perimeter and purchase price mechanism clearly. Identify transferred shares, the treatment of shareholder loans and leakage, and the adjustments for agreed cash, debt and working capital where applicable. Agree who retains historic receivables, support-related adjustments and liabilities arising from the period before closing. Pair general warranties with project-specific warranties about licences, capacity, grid access, land rights, material contracts and claims. Review the disclosure letter against the issues specifically identified in due diligence.

Set closing conditions for the approvals and consents that are genuinely necessary and assign responsibility for each. Include a long-stop date and an agreed response if a regulator attaches material conditions or a consent is delayed. In the interim, require operation in the ordinary course and prompt disclosure of material outages, licence correspondence and contractual disputes, while avoiding premature transfer of operational control. Specify how the parties will document completion and who is responsible for post-closing amendments, notifications and handover to the operator.

Hypothetical example: A buyer bids for an operating wind farm whose valuation includes an expansion and a long-term offtake contract. Diligence finds that part of the expansion is absent from the acceptance records, the main access lease expires in four years, and the offtaker can terminate if control changes. A negotiated response could be to price only verified operating capacity, make the lease extension and written offtaker consent closing conditions, and discuss separate contingent consideration for the expansion. These are three different risks; a general compliance warranty does not solve all of them.

Closing checklist

Confirm the licence holder and transaction perimeter; reconcile licensed, installed and accepted capacity; clear EPDK and competition gates where applicable; obtain material lender, land and offtake consents; agree debt and security release mechanics; sign off the closing funds flow; deliver corporate transfer documents and registers; and assign owners and timing for every post-closing filing and operational handover. Read the final documents against the same approved structure, including any late change to the buyer or upstream ownership chain.

Frequently asked questions

Does an indirect acquisition avoid EPDK review?

Not automatically. Include the upstream transfer in the ownership and control analysis. The legal answer depends on the licensing stage, the target’s regulated activities and the proposed transaction, not just on which entity signs the share purchase agreement.

Can the buyer rely on the seller’s historical generation data?

Use it as a starting point, then reconcile it to accepted capacity, meters, settlements, outage records and curtailment data. Document which figures are measured, which are forecasts and what assumption changes after closing.

What should stop signing or closing?

An unverified route to acquire control of a preliminary-licence holder is an issue to resolve before signing. A mandatory approval or consent, or a missing right that prevents normal operation, is generally a closing issue the SPA should address expressly. The parties should not confuse a promise to fix a problem later with documentary evidence that a required condition is satisfied.

Official sources

EPDK electricity licensing guidance · TEİAŞ grid connection and system use guidance · EPDK 2026 final YEK list · Environmental impact assessment implementation guidance · Official Gazette: Competition Communiqué 2026/2 · Competition Authority’s updated merger guidelines.

General legal information. Sources checked on 27 November 2026. Confirm the applicable rules and project documents before taking an investment decision.

Categories:

No Responses

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    Our Client

    We provide a wide range of Turkish legal services to businesses and individuals throughout the world. Our services include comprehensive, updated legal information, professional legal consultation and representation

    Our Team

    .Our team includes business and trial lawyers experienced in a wide range of legal services across a broad spectrum of industries.

    Why Choose Us

    We will hold your hand. We will make every effort to ensure that you understand and are comfortable with each step of the legal process.

    Call Now Button

    Cookie preferences