A factory can be operating, full of machinery and generating revenue without the company that runs it owning the land outright. In a Turkish organized industrial zone, or OSB, the operative right might be a preliminary allocation, a land allocation, registered title subject to restrictions, or a lease. For a buyer, that distinction determines whether the proposed deal preserves access to the site. It should be resolved before either party treats the land as an asset included in the price.

The immediate issue for a share buyer is Article 61(5) of the Organized Industrial Zones Implementing Regulation. The amendment published on 6 November 2026 states that a preliminary or land allocation is cancelled if aggregate changes in the shareholding of the company that received it exceed 49% without Ministry approval. A share purchase can therefore affect the land right even though the company itself remains in place and no deed is signed. A direct transfer of registered property raises a different question, including the OSB’s favorable opinion under Article 58(7). Neither is a substitute for the other.

Start with the parcel, not the transaction label

Ask the seller for a schedule of every cadastral parcel used by the business. Include not just the main production hall but any warehouse, loading yard, extension land or auxiliary premises. For each parcel, identify the registered owner, the entity that holds any allocation, the actual operator and the intended post-closing user. A compliant structure for the main factory can still leave the buyer without its warehouse or planned expansion area.

A preliminary allocation, or ön tahsis, is not registered ownership. Ask for the decision and contract, the payments made, the conditions still outstanding and what must happen for it to become a land allocation. A land allocation, or arsa tahsisi, is likewise a separate right from registered ownership. It has its own contract and performance history. Obtain the OSB board decision, the signed contract and all amendments, extensions, payment statements and notices. Compare the file with the actual site and with a recent registry extract rather than relying on the wording used in the information memorandum.

Registered title is a separate starting point, not a blanket clearance. Check restrictions, encumbrances and rights recorded against the parcel, including any disposal prohibition or repurchase annotation. Identify how title was obtained and whether liabilities or operating permit conditions are unresolved. If the factory is occupied under a lease, do not treat either the lessee or the landowner as interchangeable with the allocation holder. Review the actual lease and the approvals on which the existing occupation depends, then test the proposed post-closing use separately.

Share acquisition: what the 49% provision actually says

Article 61(5) addresses aggregate shareholding changes exceeding 49% without approval of the Ministry of Industry and Technology where the company has received a preliminary or land allocation. Its wording is about changes in shareholding, not simply who is called the controlling shareholder or whether the transaction has been described as a minority investment. A proposed transfer of 60% of an allocation holder is an obvious case to screen for prior approval. A smaller transfer should not be cleared by reading the current cap table in isolation.

Build a dated chronology of share transfers and capital changes from the available company and OSB records. Request the share ledger, shareholder lists, relevant resolutions, trade registry records where applicable, prior approval decisions and correspondence. Ask the seller to reconcile gaps and explain discrepancies. A cap table showing who owns the shares today does not, by itself, show what changed before. The article uses an aggregate test; this guide does not assume an aggregation start date or give a universal rule for indirect acquisitions, capital changes or how unusual steps are counted. Get a written position for the actual sequence if the result depends on such questions.

Also consider when a problem could surface. Article 61(5) provides for the OSB to examine shareholdings at the building permit, occupancy permit and workplace opening and operating licence stages. An investor taking over a site that still needs an occupancy permit, or planning to expand it, should not assume that an earlier transfer has been accepted merely because the plant is open. Ask what the OSB reviewed, when it reviewed it and what decision or permit records the outcome. A seller’s statement that nobody objected is not evidence of approval.

Direct property transfer: a separate decision and set of documents

Under Article 58(7), the regulation calls for a land registry annotation requiring the OSB’s favorable opinion for a transfer of property to a third party within its scope, including by enforcement sale. The provision concerns properties inside the zone that are not owned by the OSB. It also provides for the new buyer to be treated as accepting the former participant’s undertakings. A sale contract alone does not tell the buyer what those undertakings are or whether the site can operate under the buyer’s plan. Obtain their underlying text, including commitments about the activity or investment that are material to the deal.

For parcels whose title was transferred to participants, Article 61(2) separately restricts sale, transfer or assignment before the full debt is paid and a workplace opening and operating licence is obtained, and provides for an annotation. Obtain a current statement from the OSB showing the balance and how any agreed payment would be credited. Compare the licence with the titled parcel, the entity named in it and the business actually running there. A building permit, occupancy permit and operating licence are different evidence; none should be filed under a single generic permit label.

A sale of machinery and inventory is not inherently a sale of the site or an assignment of an allocation. Article 61(3) supplies a general rule against transfer of an allocation with specified exceptions. Do not assume an ordinary asset sale qualifies. Equally, do not infer that an OSB favorable opinion for a property transfer authorizes shareholding changes under Article 61(5). If the buyer is considering a later merger, separation of the operating company or a distinct property company, test the later step as well as the immediate acquisition. The most valuable restructuring option may be one that can wait until site rights are clear.

Evidence requests and their effect on the deal

Ask forWhat it testsPossible transaction response
Registry extracts and cadastral planOwner, boundaries, annotations and whether all premises are coveredTreat supplemental land separately until verified
Allocation decisions, contracts and extensionsRight in force, milestones, intended activity and conditionsMake live allocation status a closing deliverable
Share ledger, dated changes and past decisionsScope of Article 61(5) review and historical exposureCondition closing on required written approval; address known past breaches separately
OSB balance and receiptsOutstanding allocation debt and evidence of creditReflect agreed settlement in the funds flow
Occupancy and operating permits, and pending noticesWhether the post-closing owner and operator can use the intended siteVerify unresolved permits and model any delay in operation
OSB favorable opinion and existing undertakingsWhether the intended direct transfer can proceed and what commitments follow the landRequire a matching written opinion and disclose commitments in the deal documents

Translate the findings into signing and closing terms

If the required approval is not yet available, the parties can assess whether to sign an agreement with completion conditional on receiving it, rather than transfer the shares and then hope to obtain it. Identify the applicable authority, the affected parcel and the transaction steps the decision must cover. Agree who will submit the file, who will respond to requests and who bears the agreed costs. Determine what conditions in a decision would be acceptable. A decision that concerns a different transferee, stake or transaction sequence is not automatically enough. Ask counsel to review any interim governance or funding arrangements so they do not implement the transaction prematurely or prejudge an authority’s decision.

Put a reasonably achievable outside date in the contract, with a way to deal with decisions that are delayed, refused or materially conditional. An approval requirement does not imply an approval timetable. If the seller can do preparatory work, distinguish that work from actions that must wait. The contract can require the seller to keep allocation obligations and permit applications current and to notify the buyer of correspondence from the OSB during the interim period. Arrange for the buyer to see the filed materials and responses, not only an assurance that the filing team is on track.

Treat historical exposure and prospective authorization differently. Accurate disclosures about prior transfers and notices can support a warranty or specific indemnity, but don’t grant a land right. An escrow can secure an agreed monetary claim, but it cannot keep an allocation in force. If the plant location is essential and the risk cannot be cured or resolved before closing, consider excluding the affected asset only if a workable operating alternative exists. Where a second parcel matters primarily to an expansion, test whether the business case can support a valuation that does not assume it will be available.

Separate known sums from uncertain ones. A documented allocation balance can be addressed in the funds flow, with written evidence of the payment and allocation of the cost. A new capital commitment, an unresolved title restriction or a move to an alternative site is a different exposure. Model the realistic time and cost, including interruptions to production, customer approvals or relocation costs if relevant. That makes it possible to explain why the buyer is insisting on an approval condition rather than simply demanding a broad indemnity.

Hypothetical: a majority purchase with two adjacent parcels

A European components manufacturer agrees in principle to purchase 65% of a Turkish target. On the site tour, the seller describes both adjoining parcels as company property. The registry extract shows the target as owner of the production parcel, with an annotation. The adjoining expansion parcel is still registered to the OSB and appears in a preliminary allocation contract. The proposed price assumes a new production line can be built there.

The buyer separates the inquiries. For the operating parcel, it checks the annotation, the licence, allocation payment history and whether its post-closing structure would change the actual landowner or operator. For the expansion parcel, the 65% purchase puts the prior Ministry approval issue squarely on the table. The seller also reveals that one founder sold a stake to an affiliate before negotiations. The buyer supplies the complete history for the authority review rather than treating that earlier transfer as irrelevant or applying its own counting date.

In this scenario, the buyer does not accept the seller’s proposal to sign the shares over immediately and seek clearance later. It considers a conditional agreement with a separate requirement that the preliminary allocation still be in force at completion. If the Ministry decision does not cover the planned structure or the parcel cannot support the expansion, the parties must reassess the price or walk away. If they explore buying just the factory asset, that is a different structure: they must test the title transfer, OSB opinion, possible restrictions and continuing ability to operate. It does not give them the preliminary allocation automatically.

Closing checklist

  1. Map the cadastral identity, registry owner, allocation holder and operator for every parcel needed on day one or for a priced expansion.
  2. Obtain the signed preliminary or final allocation records, current title and annotations, parcel obligations, extensions and notices.
  3. Reconcile the historical shareholding changes and send the proposed pre-closing, closing and post-closing steps for transaction-specific review.
  4. Verify the scope and authenticity of any required Ministry approval and OSB favorable opinion. Do not count an application or informal message as a decision.
  5. Reconcile the debt balance, operating licence and any other permit milestones with the parcel and operating entity. Assign responsibility for satisfying outstanding items.
  6. Check that the executed transaction documents match the approved structure. Date and retain the parcel extracts, decisions and supporting records used for closing.
  7. If the proposed ownership, activity or site footprint has changed since approval, stop and recheck whether that change affects the decision before implementing it.

Frequently asked questions

Does a 49% purchase automatically avoid Ministry approval?

No automatic clearance follows from that number alone. Article 61(5) refers to aggregate changes exceeding 49%, not just the stake being bought today. The buyer needs the earlier ownership history and a clear view of how the actual deal is treated. A transaction that does not engage that provision may still involve other rules, contractual obligations or approvals.

Is the rule just for factories that are not yet operating?

The provision is framed by the existence of a preliminary or land allocation, not simply whether the site is operating. Within one business the main production parcel may already have registered title while an expansion parcel remains allocated. Check each parcel and obtain evidence of how the rights and permits are held. The current operating status of one building does not resolve the status of another parcel.

Does a title deed eliminate the need for OSB diligence?

No. It changes the diligence questions. Review the applicable restrictions, registered annotations, payment and permit history and the proposed use. For a property transfer within Article 58(7), check the favorable opinion and obtain the previous participant’s undertakings. Do not treat a clean-looking copy of the deed as a substitute for a current full registry extract and the underlying records.

Can a cancelled allocation always be restored?

No. Article 61(5) contemplates a possible new allocation at the current price, with credit for amounts already paid as described in the provision. It is not an entitlement to the old terms or a reliable fallback for closing. Underwrite the deal on continuation of the actual right, or on a distinct replacement that has been verified and documented.

What should the buyer decide first?

Decide which land rights are indispensable to the price and operating plan. Then confirm which entities hold those rights and what the proposed deal changes. For a site the buyer cannot do without, a vague assurance that the matter can be dealt with later is not an adequate substitute for verifying that the approvals and rights on which closing depends are in place.

Official sources

Official Gazette, 6 November 2026: OSB regulation amendment; Ministry consolidated regulation, particularly Articles 58 and 61; Ministry allocation guidance, section 10. Read the guidance alongside the current regulation.

This guide describes the framework as of 28 November 2026 and does not determine the treatment of a particular parcel or transaction.

Categories:

No Responses

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    Our Client

    We provide a wide range of Turkish legal services to businesses and individuals throughout the world. Our services include comprehensive, updated legal information, professional legal consultation and representation

    Our Team

    .Our team includes business and trial lawyers experienced in a wide range of legal services across a broad spectrum of industries.

    Why Choose Us

    We will hold your hand. We will make every effort to ensure that you understand and are comfortable with each step of the legal process.

    Call Now Button

    Cookie preferences